| HS Code | 251853 |
| Product Name | SikaFiber Force 400 - Embossed Macro Synthetic Fiber |
| Fiber Type | Macro synthetic fiber |
| Material | Polypropylene |
| Surface Texture | Embossed |
| Color | Natural |
| Length | 40 mm |
| Equivalent Diameter | 0.8 mm |
| Aspect Ratio | 50 |
| Tensile Strength | 400 MPa |
| Elastic Modulus | 4 GPa |
| Density | 0.91 g/cm³ |
| Melting Point | 160 °C |
| Alkali Resistance | Excellent |
| Water Absorption | Nil |
| Recommended Dosage | 3-6 kg/m³ |
As an accredited SikaFiber Force 400 - Embossed Macro Synthetic Fiber factory, we enforce strict quality protocols—every batch undergoes rigorous testing to ensure consistent efficacy and safety standards.
| Packing | SikaFiber Force 400 is supplied in 1 lb (0.45 kg) water-soluble bags, with 40 bags per 40 lb carton. |
| Container Loading (20′ FCL) | SikaFiber Force 400 embossed macro synthetic fiber loaded in a 20′ FCL dry container, palletized, shrink-wrapped, secured, and evenly distributed within payload limits. |
| Shipping | SikaFiber Force 400 is typically shipped in sealed, moisture-resistant bags or boxes, palletized and shrink-wrapped. It is generally non-hazardous and not classified as dangerous goods for transport. Store dry, away from direct sunlight and moisture. Follow the SDS and local shipping regulations. |
| Storage | Store SikaFiber Force 400 in a cool, dry, well-ventilated area, protected from direct sunlight, moisture, heat, and ignition sources. Keep bags closed in original packaging on pallets, off the ground, away from chemicals and sharp objects. Avoid excessive stacking or damage. Store at moderate temperatures, and follow local regulations and the safety data sheet for shelf life and handling. |
| Shelf Life | Shelf life: 24 months from production when stored dry, in original unopened packaging, protected from direct sunlight and excessive heat. |
For precast segment ring production, SikaFiber Force 400 functions as a Class II macrofibre under EN 14889-2:2006 and, where North American specifications govern, as a Type III synthetic fibre under ASTM C1116/C1116M-23. The addition rate is normally held between 3.5 and 5.0 kg/m³, corresponding to approximately 0.38–0.55 vol% fibre at a polyolefin density of 0.91 g/cm³; the upper bound is not determined by flexural toughness alone but by the segment demoulding envelope when vacuum-lifting anchors are cast into the segment. Batching on plants equipped with 2.5–3.0 m³ twin-shaft compulsory mixers follows a controlled sequence: coarse aggregate and cement are dry-mixed for 20–30 s, the fibre is introduced through a vibrating dosing gate over 15–25 s, and wet mixing continues for 60–90 s before discharge. Shorter wet mixing times have been observed on carousel segment lines to produce fibre agglomerates in the leading third of the discharge chute, causing locally reduced residual strength in notched beam specimens. The production process after mixing consists of pouring into segment moulds, external high-frequency vibration, steam curing at 55–65°C with a ramp-up rate not exceeding 15°C/h, and demoulding only after cube compressive strength reaches at least 15 MPa as measured by EN 12390-3 when lifting anchors are present. Terminal products are precast concrete tunnel segment rings, shaft lining segments, and cut-and-cover tunnel wall panels.
A second process pathway exists in carousel plants with 20-minute rotation targets. Batch-to-batch variance in residual strength is dominated less by cement content than by fibre dispersion quality, which is tracked by batching moisture probes and by comparing mixer amperage draws during fibre addition. When the embossed fibre is charged into a dry mix with very low moisture, electrostatic attraction can cause the fibres to cling to mixer walls and discharge gates; this failure mode is mitigated by pre-conditioning the fibres in their packaging and by injecting a small quantity of batch water before fibre addition. The use of a 0.5 mm embossed monofilament geometry contributes to pull-out resistance through mechanical deformation of the fibre surface, but this same geometry makes the fibre more sensitive to clumping under incorrect charging sequence than a smooth monofilament. Acceptance testing is performed by EN 14651:2005+A1:2007 notched beams to determine fR1 and fR4 residual flexural tensile strength; project specifications commonly require verification at the nominated dosage, although published data for this specific configuration at all curing ages remains limited.
| Application scenario | Standard designation | Measured or controlled attribute |
|---|---|---|
| Precast tunnel segments | EN 14651:2005+A1:2007 | Residual flexural tensile strength fR1, fR4 |
| Wet-mix shotcrete | ASTM C1550-20 / EN 14488-5 | Round panel energy absorption at central deflection |
| Industrial slab-on-ground | ASTM E1155-20 | FF/FL floor flatness and levelness protocols |
| Precast culverts and pipes | ASTM C1433/C1433M / EN 1916:2002 | Section geometry, proof load, absorption characteristics |
| Marine hydraulic concrete | EN 206:2013 / BS 8500-1 | Exposure class XS2/XS3 and limiting water-cement ratio |
| Port pavements | ASTM C1116/C1116M-23 / ACI 360R-10 | Type III synthetic fibre specification and slab design input |
At addition rates between 4.0 and 6.0 kg/m³, the fresh-state pumpability boundary of wet-mix shotcrete containing SikaFiber Force 400 is governed primarily by the fibre length relative to the delivery line diameter and by the paste volume of the base mix. With a nominal fibre length of 40 mm and a 50 mm delivery hose, a positive-displacement piston pump can typically convey the material over 80–120 m horizontal distance when the slump at the pump hopper is maintained at 160–200 mm. The placement process is executed with reference to EFNARC 1996 European Specification for Sprayed Concrete and ACI 506R-16, with fibre compliance under EN 14889-2:2006 Class II. The downstream production route consists of wet-mix batching, transfer into a positive-displacement piston pump, compressed air injection at the nozzle, and optional dosing of an alkali-free accelerator at 3–8% by weight of cement to control early-age adhesion. One field failure mode observed on drill-and-blast tunnel headings is nozzle block pack-out when the aggregate skeleton contains a high proportion of 8 mm maximum aggregate and insufficient fines; this bottleneck is corrected by raising the binder paste volume and by reducing fibre dosage to the lower half of the range until pump pressure stabilizes. Terminal products are permanent fibre-reinforced tunnel linings, temporary support for drill-and-blast headings, slope stabilization panels, and portal face protection shells.
Rebound behaviour and accelerator compatibility introduce a second operational boundary. During robotic spraying, nozzle angle and air flow must be adjusted to hold rebound between 10% and 20%; higher rebound preferentially removes low-density synthetic fibres from the placed material, which can leave a lean layer behind the sprayed surface. Experience on mechanized spraying rigs with 15–20 m³/min compressed air supply shows that the pressure drop across a 50 m delivery line increases non-linearly as fibre dosage exceeds 5.5 kg/m³ in the presence of a 4.0 mm maximum aggregate mix. Toughness acceptance uses ASTM C1550-20 round panel testing or EN 14488-5 energy absorption; project specifications commonly express acceptance in terms of energy absorption at 25 mm central deflection, but published universal thresholds for this specific configuration are not available.
High-bay warehouse floor construction with laser screed placement equipment exposes a conflict between SikaFiber Force 400 surface reinforcement and finishing operations. At a dosage of 3.0–4.0 kg/m³, the fibre is batched into ready-mixed concrete supplied under ASTM C94/C94M and EN 206:2013; the slab design is typically executed under ACI 302.1R-15 and TR34 4th edition, with floor flatness measured by ASTM E1155-20 FF/FL protocols. The embossed surface of the macrofibre increases pull-out resistance but also causes fibre protrusion at the trowelled surface if the final floating pass is performed before the bleed water sheet has fully evaporated. On ride-on power trowels equipped with combination blades, the standard sequence of open float, refloat, and burnish is modified by adding one pan-float pass after initial strike-off; this presses slightly raised fibre ends below the surface before the paste hardens. The production process comprises pump placement, dual-roller power screed or laser screed strike-off, restraightening, a waiting period until surface sheen disappears, and power trowelling in multiple passes. Saw cutting of contraction joints is performed at 24–48 hours after final finish, at a depth of one-third of the slab thickness, with early-entry saws where thin sections are used. Terminal products are distribution centre floor slabs, high-rack warehouse slabs, and manufacturing mezzanine decks cast on ground; the synthetic fibre is not a substitute for structural steel in suspended slabs, and published data for this specific configuration is limited concerning long-term creep under very tall racking loads.
When precast culvert and drainage product manufacturers replace conventional welded wire mesh in wet-cast box culvert walls, the addition rate for SikaFiber Force 400 is set between 4.0 and 5.0 kg/m³, with fibre compliance under EN 14889-2:2006 Class II and product dimensions under ASTM C1433/C1433M or EN 1916:2002. The production process uses a 1.5 m³ pan mixer or 2.0 m³ planetary counter-current mixer; after a 30 s dry mix of aggregate and cement, the fibres are added via a vibrating dosing gate to prevent balling, followed by water and high-range water reducer addition. The wet-cast mix is poured into steel moulds and consolidated with high-frequency external vibrators operating at 12,000–15,000 vpm for 20–30 s per mould side; excessive vibration beyond this window visibly drives the lower-density synthetic fibre toward the top surface, producing an anisotropic distribution observed on cut sections. The demoulded elements are cured in a mist chamber at 90–95% RH and 20–23°C for 48–72 hours before mechanical handling. Terminal products include box culverts, storm drainage manholes, side entry pits, and precast U-channel drains. For dry-cast pipe production with zero-slump concrete, the fibre is not recommended due to inadequate dispersion and surface finish degradation; published data for this specific configuration is limited, and this operational boundary should be verified by plant trials.
The decision to remove conventional steel mesh is not purely a fibre dosage decision. In culvert walls, the fibre contributes to crack-width control after first cracking, but it does not provide the same structural lever arm as continuous bar reinforcement under high earth pressure. Short- and long-term load capacity is therefore evaluated by project-specific structural testing rather than by fibre content alone. On production lines with repeated daily pours, batch-to-batch flow differences are most pronounced when recycled wash water is used in the batching sequence; the fibre can adhere to recycled water sludge in the mixer, causing inconsistent dispersion. This has been controlled by limiting wash water to 10% of total mix water and adding it before the fibre rather than after.
In tidal and splash-zone marine works, SikaFiber Force 400 is incorporated into cast-in-place quay capping beams and wave return walls at 4.0–5.0 kg/m³, where compliance is referenced to BS 6349-2 for maritime structures and EN 206:2013 exposure classes XS2 and XS3, with a maximum water-cement ratio of 0.45 and minimum cover to reinforcement as defined by BS 8500-1. The embossed macrofibre contributes to crack-width control under thermal restraint and wave loading, but it does not reduce the chloride diffusion coefficient below the binder-dependent threshold; therefore, the concrete design continues to require supplementary cementitious materials such as ground granulated blastfurnace slag at 50–70% cement replacement. The production process involves site batching, crane-hopper placement, and high-frequency internal vibration with poker diameters not exceeding 50 mm; fibre clumping at the hopper discharge has been observed when the first batch of the day is placed after excessive predose water, a production bottleneck traced to water line bleed-back. Terminal products are quay edge beams, wave return walls, breakwater access decks, and concrete revetment facing panels. Published data for this specific configuration in long-term tidal cycling is limited; plant-specific durability tests should be performed for XS3 exposure.
Container yard pavements and intermodal handling areas require crack-width control under concentrated wheel loads from reach stackers and straddle carriers, and SikaFiber Force 400 is added at 3.5–4.5 kg/m³ to ready-mixed concrete according to ASTM C1116/C1116M-23 Type III synthetic fibre specification and ACI 360R-10 design guidance for slabs on ground. The pavement construction process includes direct pump placement, laser-guided strike-off with a dual-roller screed, and joint construction per ASTM E1155-20 FF/FL evaluation; the dosage selection is limited by the requirement to maintain a 150–175 mm slump without segregation under sustained truck-delivery times of 45–60 minutes. Plant experience indicates that macrofibre reinforced mixes with total aggregate fines exceeding 48% of total aggregate weight tend to increase pumping back-pressure and can cause hose blockages if the pump line has a 125 mm diameter and a horizontal run longer than 300 m. Terminal products are container yard concrete pavements, intermodal rail corridor slabs, truck apron strips, and heavy-duty maintenance hardstandings. The synthetic fibre does not replace steel dowel assemblies at joints; joint load transfer relies on the dowel system and aggregate interlock, not on fibre bridging alone, and published data for this specific configuration under repeated reach stacker passes is limited.
Competitive SikaFiber Force 400 - Embossed Macro Synthetic Fiber prices that fit your budget—flexible terms and customized quotes for every order.
For samples, pricing, or more information, please contact us at +8618112911328 or mail to sales1@liwei-chem.com.
We will respond to you as soon as possible.
Tel: +8618112911328
Email: sales1@liwei-chem.com
Flexible payment, competitive price, premium service - Inquire now!
SikaFiber Force 400 - Embossed Macro Synthetic Fiber is a polyolefin-based macro fiber supplied as discrete cut monofilaments with a deformed surface profile. The product is identified as a Type III synthetic macro fiber under ASTM C1116/C1116M-23. Nominal manufacturer-published data include a cut length of 40 mm, an equivalent diameter of 0.85 mm, a specific gravity of 0.91 g/cm³, a minimum tensile strength of 600 MPa, and an elastic modulus of approximately 6 GPa. The embossed surface is intended to provide mechanical interlock with the cementitious matrix beyond the frictional resistance of smooth monofilament fiber. At an addition rate of 4 kg/m³, the calculated fiber volume fraction is approximately 0.44%; at 6 kg/m³, it is approximately 0.66%. The product is used in industrial floor slabs, slabs on grade, composite metal deck slabs, sprayed concrete linings, tunnel segments, and precast elements where post-crack flexural toughness or energy absorption is required. The fiber dosage cannot be selected from mass alone because residual strength is matrix-dependent and must be verified under the applicable test standard.
| Designation | Published value | Test basis |
|---|---|---|
| Fiber type | Type III synthetic macro fiber | ASTM C1116/C1116M-23 |
| Nominal length | 40 mm | Manufacturer data sheet |
| Equivalent diameter | 0.85 mm | Manufacturer data sheet |
| Specific gravity | 0.91 g/cm³ | ISO 1183-1:2019 |
| Minimum tensile strength | 600 MPa | ASTM D638-14 |
| Elastic modulus | 6 GPa | ASTM D638-14 |
| Melt point | 160 °C | ISO 3146:2019 |
The mass-based dosage of steel fiber is commonly 20 kg/m³ to 40 kg/m³, whereas macro synthetic fiber addition is typically 4 kg/m³ to 8 kg/m³. The difference arises from the specific gravity of steel at approximately 7.85 g/cm³ compared with 0.91 g/cm³ for SikaFiber Force 400. For a fixed fiber count per cubic metre, the synthetic product requires less added mass; however, the elastic modulus of polyolefin fiber is roughly 6 GPa, while structural steel fiber values are typically near 200 GPa. Equal mass replacement of steel fiber with macro synthetic fiber is therefore not valid without re-evaluating residual flexural strength under ASTM C1609/C1609M-19a or EN 14651. The polyolefin fiber contains no metallic phase and does not contribute to chloride-induced corrosion or rust staining, which is a relevant boundary in slabs exposed to deicing salts or marine aerosols. In contrast, microsynthetic fibers with lengths below approximately 12 mm are generally intended for plastic shrinkage crack reduction and are not considered primary post-crack reinforcement. The structural function of SikaFiber Force 400 depends on fiber length, aspect ratio, and embossed surface deformation, which enable load transfer across cracked sections after the cement paste has cracked. Among macro synthetic products, the embossed profile differentiates SikaFiber Force 400 from smooth monofilament and fibrillated fiber geometries; smooth fibers rely mainly on frictional pullout, while the embossed fiber mobilizes additional mechanical interlock, although published direct pullout data for this specific geometry is limited and should be generated on the project mix.
| Parameter | SikaFiber Force 400 | Structural steel fiber | Relevance |
|---|---|---|---|
| Specific gravity | 0.91 g/cm³ | 7.85 g/cm³ | Mass dosage differs at equal fiber count |
| Tensile strength | 600 MPa | 1000–2000 MPa | Post-crack stress transfer is lower |
| Elastic modulus | 6 GPa | 200 GPa | Deflection control differs; direct substitution is not valid |
| Corrosion potential | None, polyolefin non-metallic | Carbon steel may rust at exposed surfaces | Chloride exposure and exposed concrete surfaces |
| Typical dosage | 4–6 kg/m³ | 20–40 kg/m³ | Mass-based comparison is not equivalent |
Fibre conformity for structural concrete is specified through EN 14889-2:2006, under which polymer fibres are classified as Class II when used for structural purposes. Specifiers should verify the CE certificate for the specific production plant because conformity depends on factory production control. Under ASTM C1116/C1116M-23, synthetic fibers are Type III materials, and acceptance is based on the manufacturer’s certified properties. For flexural performance, ASTM C1609/C1609M-19a defines first-peak and residual strengths f1, f600D, and f1500D using a closed-loop third-point bending beam. EN 14651:2005+A1:2007 defines flexural tensile strength and residual strengths fR1 and fR3 at crack mouth opening displacements of 0.5 mm and 2.5 mm. Shotcrete energy absorption is evaluated under EN 14488-5:2006 or ASTM C1550-20 using panel specimens. These standards do not assign a fixed dosage to the fiber; they provide test methods for verifying whether a chosen fiber dosage delivers the required residual strength or energy absorption in a specific concrete mixture.
For industrial slabs on grade, macro synthetic fiber dosage is commonly specified between 4 kg/m³ and 6 kg/m³. At 4 kg/m³, the calculated volume fraction is approximately 0.44%, and at 6 kg/m³ it is approximately 0.66%. The resulting residual strength depends on concrete compressive strength class, coarse aggregate type, water-cement ratio, and batching sequence. In shotcrete linings, dosages of 5 kg/m³ to 8 kg/m³ are often tested under EN 14488-5:2006 to determine panel energy absorption. A higher dosage does not produce a linear increase in residual flexural strength in all mixes; the incremental benefit is dependent on fiber orientation and matrix density. In a typical cast beam test under EN 14651, the residual strength values fR1 and fR3 must be measured on the project-specific concrete because changes in coarse aggregate shape and paste volume can alter fiber pullout and orientation. Production-scale batching in twin-shaft compulsory mixers has shown that dosage uniformity can be influenced by mixer wear and paddle clearance; maintaining the mixer condition is critical to avoiding fiber accumulation in dead zones. Field batch records from slab-on-grade placements indicate that adding the fiber at the same time as the coarse aggregate can reduce visible fiber balling, while adding it at the end after free water can lead to localized clumping in low-slump mixtures. These observations are operational and do not replace trial batching under the relevant standard.
In slab-on-grade construction, the product is typically added at dosages of 4 kg/m³ to 6 kg/m³, with saw-cut spacing and joint design remaining unchanged unless a jointless slab design is validated. In composite metal deck slabs, macro synthetic fibers are used to supplement or replace welded mesh in certain designs, but the deck profile and concrete cover requirements control fiber distribution near the rib corners. In precast tunnel segments, the product may reduce surface bursting cracks and improve handling durability; batching trials in segment plants with twin-shaft compulsory mixers and automated fiber conveyors are commonly required. In shotcrete, the use of a lower-density fiber changes rebound behavior compared with steel fiber; field trials under EN 14488-5:2006 or ASTM C1550-20 are used to verify the achieved energy absorption because nozzleman technique and air pressure influence fiber retention. Published data for this specific product configuration in full-scale tunnel segment applications is limited, and project-specific qualification is required.
In ready-mix concrete, the fiber is introduced into the drum and mixed for a prescribed revolutions count, typically after the initial batching of aggregates and cement has been wetted. For twin-shaft plant mixers, addition with aggregates is preferred because the aggregates act as a dispersing medium and reduce fiber-to-fiber contact. Dry mixing of macro fiber with fine powders in high-shear mixers is not recommended because electrostatic charge and mechanical entanglement can produce balling. When the coarse aggregate fraction exceeds approximately 50% by volume of total aggregate, the dispersal path is more aggressive and the observed balling rate is lower. Batch-to-batch variance in fiber distribution is monitored through washout tests of fresh concrete and residual strength testing of beam specimens. A high-range water reducer conforming to ASTM C494/C494M-19 may be used to restore workability after fiber addition, but the addition sequence should be adjusted so that free water does not lubricate fiber clumps before dispersion. The mixer should be inspected for buildup on paddles and shafts, because fiber accumulation behind worn scrapers can create intermittent dosage spikes. No single mixing time is universally valid; a starting point of 5 min after the last component is common in plant trials but must be confirmed for each mixer geometry.
SikaFiber Force 400 is not intended to replace conventional continuous reinforcement in structural elements unless the design explicitly accounts for residual flexural or tensile strengths under EN 14651 or ASTM C1609/C1609M-19a. The product should not be used as the sole reinforcement in applications where minimum ductility is required by code in the absence of standardized tests. The fiber is compatible with normal Portland cement and supplementary cementitious materials, but batching trials are required when silica fume or high-volume fly ash alters paste rheology. Polyolefin fibers should not be exposed to oxidizing acids or strong hydrocarbon solvents in service; published data for chemical resistance in concentrated acidic environments is limited. In installations where surface abrasion is governed by ASTM C944/C944M-12 or similar methods, the steel-trowel finish may expose fibers at the surface, which can be controlled by mechanical finishing or by the application of a dry-shake hardener. Storage should be in dry conditions; the fiber itself is non-absorbent, but water-soluble packaging, where supplied, may require protection from moisture. No thermal activation or pre-treatment is required before mixing, and the product does not require pre-drying.